Project schedule
9/21-10/5
- Technology Evaluation & Assessment
- Critical application features assessment
- System requirements
- Data Access issues
9/28-10/19
- Application Design
- Database Design
- Data Access, Integration and Engineering
- Interface Design
10/5-11/16
- Application Implementation
- Install and set up database, Web server, Database gateway, Java
applets, etc.
- Configure database, Web server, Database gateway, Java applets
- Interactive Map preparation
- Load data into system
- Test server and system scalability
- Debugging (to occur throughout project)
11/30
|