|
Actions |
Weeks |
Depends on |
A |
Establish suitability of building |
3 |
- |
B |
Feasibility/plan/cost telecommunications |
3 |
- |
C |
Estimate remodelling cost of building |
1 |
A |
D |
Get funding approved |
3 |
B,C |
E |
Appoint project manager |
1 |
D |
F |
Select architect for remodelling |
4 |
D |
G |
Preparation of working drawings |
5 |
F |
|
Optimistic 4 weeks; pessimistic 6. |
|
|
H |
Select contractor |
4 |
G |
I |
Remodelling (incl. telecommunications) |
6 |
H |
|
Optimistic 5, pessimistic 7. |
|
|
J |
Select/order equip for parallel operation |
3 |
E |
K |
Take delivery of equip at new site |
3 |
J |
L |
Establish parallel operations |
2 |
I,K |
M |
Certify operations at new site O.K. |
3 |
L |
N |
Discontinue/dismantle old site |
4 |
M |