| Actions | Weeks | Depends on | |
| A | Establish suitability of building | 3 | - |
| B | Feasibility/plan/cost telecommunications | 2 | - |
| C | Estimate remodelling cost of building | 1 | A |
| D | Get funding approved | 3 | B,C |
| E | Appoint project manager | 1 | D |
| F | Select architect for remodelling | 4 | D |
| G | Preparation of working drawings | 5 | F |
| Optimistic 4 weeks; pessimistic 6. | |||
| H | Select contractor | 4 | G |
| I | Remodelling (incl. telecommunications) | 6 | H |
| Optimistic 5, pessimistic 7. | |||
| J | Select/order equip for parallel operation | 3 | E |
| K | Take delivery of equip at new site | 3 | J |
| L | Establish parallel operations | 2 | I,K |
| M | Certify operations at new site O.K. | 3 | L |
| N | Discontinue/dismantle old site | 3 | M |